KleverStock

Malakoff’s 3Q revenue climbs 34%, plant recovery lifts 4Q outlook

Published 27 November 2026, 06:58 pm Updated 27 November 2026, 07:52 pm The Malaysian Reserve

MALAKOFF Corporation Bhd’s third-quarter revenue rose 33.8% to RM2.26 billion as its coal-fired plants in Johor earned higher energy payments and its gas-fired plant in Lumut, Perak, generated more electricity.

The group expects the return of its Tanjung Bin Power Plant to full capacity to support revenue and earnings from the fourth quarter.

Profit attributable to equity holders was RM27.76 million for the quarter ended Sept 30, 2026 (3Q26), down 1.6% from RM28.21 million a year earlier.

Higher contributions from associates helped cushion the impact of the earlier turbine failure at Tanjung Bin’s Unit 30.

The year-earlier quarter also benefited from the reversal of a provision against the value of coal inventories.

Malakoff said in its Bursa Malaysia filing that higher applicable coal prices lifted energy payments at both Tanjung Bin plants, while the grid operator called for more generation from the Lumut gas plant.

After distributions to the perpetual sukuk holder, profit attributable to ordinary shareholders was RM0.1 million, compared with RM0.4 million a year earlier. The board did not recommend a dividend for the quarter.

Tanjung Bin restored, GB3 returns early

Unit 30 resumed base-load generation on Aug 9, restoring Tanjung Bin Power Plant to full capacity.

“While the earlier disruption is still reflected in this quarter’s profit, we are heading into the final quarter of the year in a stronger position,” said group CEO Syahrunizam Samsudin.

Malakoff’s 429-megawatt (MW) GB3 gas-fired plant in Lumut resumed commercial operations on Oct 7, nearly three months ahead of schedule, under a power purchase agreement with Tenaga Nasional Bhd that runs through December 2029.

With the Prai Power Plant operating since April, Malakoff now has seven operational power plants in Malaysia, including the jointly owned Kapar Power Plant, with a combined capacity of 7,382 MW.

Malakoff said both coal-fired plants at the Tanjung Bin complex continued generating power after a conveyor belt fire on Nov 19.

Repairs are expected to be completed by the end of November, subject to testing and commissioning.

The Sustainable Energy Development Authority also approved a higher average feed-in tariff and a capacity increase for Malakoff’s three small hydropower plants in Kelantan.

Their combined installed capacity is set to rise by about 14% to 95.67 MW.

Alam Flora profit rises 28%

Malakoff’s environmental solutions business, led by Alam Flora, posted a 28% increase in quarterly net profit to RM22.5 million, helped by tighter cost management.

The business accounted for about 10% of group revenue and won new contracts covering public infrastructure, industrial facilities and warehouses.

Malakoff subsidiary Sungai Udang WTE Sdn Bhd is establishing a RM700 million ASEAN green sukuk programme to partly finance Melaka’s first waste-to-energy facility.

The plant is expected to treat up to 1,056 tonnes of municipal solid waste a day when completed in 2029.

For the first nine months, revenue was RM5.55 billion, down 3.4%, while profit attributable to equity holders fell 36.4% to RM79.58 million from RM125.03 million.

Malakoff attributed the weaker nine-month performance mainly to earlier disruptions at Tanjung Bin’s Units 20 and 30. – TMR